North Water Reclamation Facility Phase 1A Improvements
Location
Parker, COValue
$57MDelivery Method
CMARClient Type
MunicipalProject Type
- Plant
Parker Water & Sanitation District’s existing North Water Reclamation Facility was in need of upgrades and expansion to continue serving its growing community of more than 18,000 customers. The District selected Garney as its construction manager at risk (CMAR) to provide these needed improvements.
Garney expanded the facility from 2 million gallons per day (MGD) to 3.8 MGD. The scope of work included a new headworks facility, the addition of primary clarification, expansion of the advanced water treatment (AWT) equalization and pumping capacity, replacement of chlorine disinfection with ultraviolet disinfection (UV), conversion of existing aerobic digesters to autothermal thermophilic aerobic digestion (ATAD), capacity upgrades to the dewatering facilities, and new primary plant power, metering, and distribution.
One of the greatest challenges Garney overcame on this project included the multiple process and electrical tie-ins required to expand the existing facility without affecting plant operations. This included a full plant bypass to tie in a new plant influent manhole. The project team worked closely with District staff to maintain plant operations and effluent requirements.
These improvements by Garney provided new life to the facility and will allow for continued future expansion of the District’s asset and the community it serves.